Dublin Airport North Apron Project

Client
Clare Civil Ltd
Value
€420,000
Duration
10th Feb 2020 to September 2020

LAML was contracted by Clare Civil Ltd to undertake saw cutting and sealing of new and existing Pavement Quality Concrete (PQC) bays, existing PQC slab repairs and removal of existing defective PQC bays.

Our subcontract package consisted of:

  • 7,157m of saw cut and seal in new PQC construction
  • 30,000m of routing out of existing sealant
  • 30,000m of sealing existing PQC joints
  • 13 PQC slab repairs using Maxicrete
  • Coring of existing defective PQC bays in preparation for removal
Dub Case 2